Use the Work Order Timesheet Information subtask to enter work order timesheet data for this timesheet line.
You can enter work orders on the Manage Work Orders screen. Use this subtask to enter data about the work order to which this timesheet is being charged.
Work Order
| Field |
Description |
| Work Order |
Enter, or click to select, a work order number to which this timesheet is charged. This is a required field. |
| Status |
This field displays the status of the selected work order. |
| Project |
This field displays the project to which the selected work order has been assigned. |
| Cost Element ID |
This field displays the cost element ID associated with the work order. |
Routing Operation
| Field |
Description |
| Operation Sequence |
Enter, or click to select, the operation sequence number of the routing operation for this work order. |
| Operation Step |
Enter, or click to select, the step number of the routing operation that is associated with this work order. |
| Routing Description |
This field displays the descriptions for both the Operation Sequence number and the Step number, if that information is available. |
| Activity Type |
From the drop-down list, select Run to record hours against a work order or Set Up to record setup hours. |
| Work Center |
Enter, or click to select, a work center ID to which this timesheet is charged. The name or description of the work center is displayed in the field to the right. |