Use this screen to modify the parameters used to download Manufacturing Order (MO) and Work Center information from Costpoint into the RSS Advanced Planning and Scheduling (APS) system.
Use this group box to select whether the APS scheduled date should be populated with the MO planned release date or in shop dates.
Select this option to load the MO Planned Release Date as the Scheduled Release Date.
Select this option to load the MO Planned Shop Date as the Scheduled Release Date.
Select this check box to calculate whether required purchased inventory is on hand and available for each MO.
Select this checkbox to include the part revision in the APS make part field.
Use this group box to select whether operations should be scheduled forward from the start date or back from the due date as a default.
Select this option to use Forward Scheduling as the default for planning MO operations.
Select this option to use Backward Scheduling as the default for planning MO operations.
Enter a number (1-10) to use as the default priority for new MOs (1 - highest, 10 - lowest).
Use this group box to select a user-defined field if you wish to export that routing line field's value as a work center pool.
Select this option if you do not want to export the any user-defined field's routing line value as a work center pool.
Select this option if you want to export this user-defined field's routing line value as a work center pool.
Select this option if you want to export this user-defined field's routing line value as a work center pool.
Select this option if you want to export this user-defined field's routing line value as a work center pool.
Use this group box to indicate user-defined field numbers to populate with MO planner, inventory abbreviation, netting group, order reference, or assembly serial number fields.
Enter a user-defined field number (1-9) to populate with the MO planner.
Enter a user-defined field number (1-9) to populate with the MO build-to inventory abbreviation.
Enter a user-defined field number (1-9) to populate with the MO build-to Project's netting group.
Enter a user-defined field number (1-9) to populate with the MO order reference number.
Enter a user-defined field number (1-9) to populate with the MO assembly serial numbers.
Use this group box to select the source notes field to be loaded to the APS MO notes field.
Select this option to download MO header notes.
Select this option to download MO expedite notes.
Select this option to not download MO notes.
Use this group box to select the source of the APS Work Center Department.
Select this option to download the work center's organization ID as the APS Work Center department.
Select this option to download the work center's type as the APS Work Center department.
Select this option to download load the entered value as the APS Work Center department for all work centers. Enter the value to assign as the department for all downloaded work centers in the field to the reight.
Enter the default alternate file location uploaded/downloaded files should be stored at.
Use this group box to select how the system should try to link subassembly MOs to assembly jobs.
Select this option to have the system try to link subassemblies to assembly jobs by part and order reference number.
Select this option to have the system try to link subassemblies to assembly jobs by part and inventory abbreviation.
Enter the calendar days difference allowed between the need date of the subassembly and parent requirements when linking jobs. Enter the number of calendar days in the field to the right.
Select this option to not have the system try to link subassemblies to assembly jobs.
Use this group box to select whether the APS system should update Costpoint operation dates, or vice-versa.
Select this option to have the APS system updated with Costpoint Actual Operation Start and Completion Dates.
Select this option to have Costpoint updated with the APS Actual Operation Start and Completion Dates.