Use this screen to group pools by a sequence number. The sequence number also drives the order in which pools are allocated. For example, pools in sequence "2" are allocated after pools in sequence "1."  It is very important that pools have the correct sequence number. If a pool allocates some of its costs to another pool or base, it must have a lower sequence number than the pool that is receiving the costs.

When should I use this screen?

Use this screen to initially set the sequence of all cost pools (including service centers) in all allocation groups. You will need to make additional changes in this screen only when you need to change sequence numbers. If you change the sequence number of any pool, you must run the Build Rate Application Table process.

Field Descriptions

Identification

Allocation Group Number

Use the Query button on the toolbar to select an allocation group and fiscal year for which to set up the pool processing sequence. Group 1 is the primary allocation group, in that all the pools in that group will allocate to projects. However, you can select any valid allocation group. This is a required field. The adjacent field displays the description of the allocation group.

Fiscal Year

This non-editable field displays the fiscal year for the allocation group/fiscal year combination selected.

Table Window

Sequence Number *

Use this column to assign a sequence number that corresponds to each pool within the allocation group. Example: If pools 1, 3, and 5 are put in sequence 1, they will allocate before pools 2 and 8, which are put in sequence 2.

Pool Number

This non-editable column displays all of the pool numbers that belong to the allocation group specified.

Pool Description

This non-editable column displays the name of each cost pool.

Recalc Base

Use this column to select the calculation of a pool base. Enter "Y" (Yes) to take the pool base amounts from the ledger for each base account/organization combination specified for the pool. Enter "N" (No) to take the pool base from the Allocation Journal. For manual service centers, this column should always be "N."

 