Use this subtask to map Project Labor Categories (PLCs) to each line.
Note: You can enter data for a given project/CLIN in only one subtask, Accounts or PLC Mapping. If you manually upload data into both subtasks for a project/CLIN, the data in the PLC Mapping subtask is used and the data in the Accounts subtask is ignored. |
This subtask is available only if the billing formula linked to the project is an LLR formula. This enables you to match specific labor resources to a CLIN. The following are considered LLR formulas:
Billing Formula |
Billing Formula Description |
CIMR |
Labor Cost Times Multiplier Plus Non-Labor Times Multiplier (Hours) |
LLR |
Loaded Labor Rate |
LLRCINBF |
Loaded Labor Plus Non-Labor W/Burden W/Fee |
LLRCINL |
Loaded Labor Plus Cost Incurred on Non-Labor |
LLRCINLB |
Loaded Labor Plus Non-Labor Plus Burden on Non-Labor |
LLRFNLBF |
LLR W/Fee Plus Non-Labor W/Burden W/Fee |
RSBFNLBF |
Loaded Labor Rate W/Burden W/Fee Plus Non-Labor w/Burden W/Fee |
RSMNLM |
Rate Schedule Times Multiplier Plus Non-Labor Cost Times Multiplier |
The charges are as follows:
Project |
Account |
PLC |
Amount |
C001.01.01 |
ENG-01 |
E01 |
50,000 |
C001.01.01 |
ENG-35 |
E35 |
15,000 |
C001.01.01 |
SUP-10 |
S10 |
10,000 |
C001.01.02 |
SUP-10 |
S10 |
25,000 |
C001.01.03 |
DIR-15 |
D15 |
60,000 |
The account mapping looks like this:
Project |
CLIN |
Starting Account |
Ending Account |
C001.01.01 |
0001AA |
ENG |
ENZ |
C001.01.01 |
0002AB |
SUP |
SUZ |
Because you have already mapped accounts to C001.01.01/0002AB, no PLCs can be mapped to this project. You must delete the accounts mapping for project C001.01.01 and then create this mapping:
Project |
CLIN |
PLC |
C001.01.01 |
0001AA |
E01 |
C001.01.01 |
0001AA |
E35 |
C001.01.01 |
0002AB |
S10 |
Use this subtask whenever you need to map PLCs.
Enter, or use Lookup to select, a PLC.
Note: The codes in Lookup are taken from the BILL_LAB_CAT table. Because a wildcard option is allowed in the Project Level At and Below field in the CLIN Mapping subtask, Lookup may not display the correct PLC codes and descriptions by project. |
This field displays the description of the PLC you selected, but you can edit it.
Changes to this subtask update the PROJ_WAWF_PLC table.