SUBCONTRACT PO LINE DETAIL

Note: This subtask is available only for subcontract POs. Otherwise, the Line Detail subtask will display. 

Use this subtask to view on-screen detail information for the selected subcontract purchase order line. These values will display for the subcontract PO from the Enter POs screen in Costpoint Purchasing. You can update this information in the Update Subcontract PO Status screen in Costpoint Purchasing.

PO

This field displays the subcontract purchase order ID.

Release

This field displays the release number of the subcontract purchase order.

Change Order

This field displays the latest change order number of the subcontract purchase order.

Line

This field displays the subcontract purchase order line number.

Misc Type

This field displays the miscellaneous charge type for the subcontract PO line.

Note: Subcontract POs can contain only "S" (Service) and "M" (Miscellaneous) line types. 

Due Date

This field displays the due date for the subcontract PO line.

Orig Due Date

This field displays the original due date for the subcontract PO line.

Desired Date

This field displays the desired due date for the subcontract PO line.

Trans Curr

This field displays the transaction currency for the subcontract PO line. The invoice for these materials will be in this transaction currency.

Item

This field displays the service ID for the line; otherwise, this field will be blank for "M" (Miscellaneous) line types. The service or miscellaneous (i.e., Misc Type) description assigned to the line will display to the right of the Rev field.

Rev

This field displays the service ID's revision for the line; otherwise, this field will be blank for "M" (Miscellaneous) line types. The service or miscellaneous (i.e., Misc Type) description assigned to the line will display to the right.

Amounts

The fields in this group box display all applicable amounts related to the subcontract PO and reflects the most recent update from the Update Subcontract PO Status screen in Costpoint Purchasing. The values in this group box display in the selected transaction currency from the Exchange Rates subtask of the Enter POs screen in Costpoint Purchasing.

Order

This field displays the current order amount of the subcontract PO line after all changes. The value in this field was originally entered as the Ext Cost Amt for the PO line in the Enter POs screen in Costpoint Purchasing. However, this field displays the most recently updated amount if any additional change orders were entered.

Completed Work

This field displays the actual work completed (i.e., cumulative from inception to date) for the subcontract PO line. The system calculates the Completed Work amount by multiplying the Percent Complete by the Subcontract Order Amount for the PO line.

Stored Materials

This field displays the value of the materials (cumulative from inception to date) that have been supplied to a site for use on a subcontract PO line item job. This amount is also included during payment voucher calculations.

Bal to Complete

This field displays the remaining amount of the subcontract order against which service is yet to be received in terms of work completed or stored materials, including retention amounts. 

The system calculates the Bal to Complete amount as follows: Subcontract Order Amt - Completed Work Amount - Stored Materials Amt (i.e., Subcontract Order Amt - Subcontract Accepted Amt). These values are from the Update Subcontract PO Status screen in Costpoint Purchasing.

Requested

This field displays the total amount of work that the vendor has stated as completed against the subcontract PO (from inception to date).

Compl Work Retn

This field displays the actual value of the completed work retention amount (cumulative from inception to date) that has been withheld from payment. This amount cannot be greater than the completed work amount for the PO line. Updates to this field will automatically modify the Completed Work Retention Pct field in the Update Subcontract PO Status screen in Costpoint Purchasing. Consequently, the Eligible for Voucher Amt and Incremental Completed Work Retention Amt will also be updated.

The system calculates this amount by multiplying the Completed Work Retention Pct field by Completed Work Amount field in the Update Subcontract PO Status screen.

Stored Matl Retn

This field displays the actual value of stored materials retention amount (cumulative from inception to date) that has been withheld from payment. This amount cannot be greater than the stored materials amount for the line. Updating the value in this field will automatically modify the Stored Materials Retention Pct field in the Update Subcontract PO Status screen in Costpoint Purchasing. Consequently, the Eligible for Voucher Amt and Incremental Stored Materials Retention Amt fields will also be updated.

The system calculates this field by multiplying the Stored Materials Retention Pct by the Stored Materials Amt in the Update Subcontract PO Status screen.

Prev Vouchered

This field displays the value of accounts payable vouchers that have been created (cumulative from inception to date) against the subcontract PO line.  These vouchers include those based on progress payment request updates (via the Create Subcontract PO Vouchers screen in Costpoint Accounts Payable), along with those manually created vouchers that are not related to any progress payment request.

Eligible for Voucher

This field displays the net amount for which additional accounts payable vouchers can be created. This value is equal to the amount still payable to the vendor less retentions. If the eligible for voucher amount is negative, this field will display zero.

The system calculates this field as follows: Completed Work Amt + Stored Materials Amt - Completed Work Retention Amt - Stored Materials Retention Amt - Prev Vouchered Amount. The values are from the Update Subcontract PO Status screen in Costpoint Purchasing.

Sales Tax/VAT Payable

This field displays the amount of sales tax/VAT due based on the line's voucher amount that is eligible for payment for the particular update. This field is calculated if the line is taxable (i.e., the Tax field is "Y" for the PO line in the Enter POs screen), and the Sales Tax/VAT Code, Sales Tax/VAT Rate, and amount payable are populated in the Update Subcontract PO Status screen. The Sales Tax/VAT Code is based on the Ship ID on the subcontract PO line.

The system calculates this field by multiplying the Eligible for Voucher Amt by the Sales Tax/VAT Rate in the Update Subcontract PO Status screen.

Posted to G/L

This field displays the amount of the subcontract PO that has been posted to the General Ledger.

Table Window

Use this table window to view charge number information for each subcontract purchase order line.  The information in this screen is non-editable, and was originally established in the Account Distribution subtask of the Enter POs screen in Costpoint Purchasing.

Project

This field displays the project assigned to the subcontract PO line in the Account Distribution subtask of the Enter POs screen in Costpoint Purchasing.

Project Name

This field displays the project name assigned to the project ID.

Organization

This field displays the organization ID assigned in the Account Distribution subtask of the Enter POs screen in Costpoint Purchasing. The organization indicates how charges are received for the line item.

Organization Name

This field displays the organization name assigned to the organization ID.

Account

This field displays the account ID assigned in the Account Distribution subtask of the Enter POs screen in Costpoint Purchasing. If the subcontract PO line has an inventory abbreviation in the Account Distribution subtask, the associated account ID displays in this field.

Account Name

This field displays the account name assigned to the account ID.

Trans Amount

This field displays the amount of this line item to be charged to the selected Account/Organization/Project based on the allocation percentage. This amount displays in the transaction currency for this subcontract purchase order and reflects the settings and the value in the Trans to Func field in the Exchange Rates subtask of the Enter POs screen in Costpoint Purchasing. If the transaction currency and functional currency are different for the subcontract PO (and an exchange rate value greater or less than "1" exists in the Trans to Func field), this field displays the in the Exchange Rates subtask of the Enter POs screen

Func Amount

This field displays the amount of this line item to be charged to the selected Account/Organization/Project based on the allocation percentage. This amount displays in functional currency for this subcontract purchase order.

Allocation

This field displays the percentage amount of this line item to be charged to the selected account/organization/project. In the Account Distribution subtask of the Enter POs screen in Costpoint Purchasing, you can delete this default percentage and enter an amount in the Amount column instead.

Ref 1

This field displays the reference 1 value assigned in the Account Distribution subtask of the Enter POs screen in Costpoint Purchasing.

Ref 2

This field displays the reference 2 value assigned in the Account Distribution subtask of the Enter POs screen in Costpoint Purchasing.

Ln Txt Codes

Select this pushbutton to view information on the subcontract PO line item's line text codes.

Line Notes

Use this pushbutton to view on-screen line notes associated with the selected subcontract PO line.

SUBCONTRACT PO-MATCH STATUS UPDATE (FOR OPEN VOUCHER)

SUBCONTRACT PO-MATCH STATUS UPDATE (FOR VOUCHER HISTORY)

SUBCONTRACT PO-VOUCHER HISTORY BY LINE

SUBCONTRACT PO OPEN VOUCHERS BY LINE