Use this non-editable subtask to view summarized amounts across all lines of the subcontract PO. You can modify these fields in the main screen for each subcontract PO line.
If multicurrency is used for the subcontract PO, this screen will display all amounts in both transactional and functional currency, as well as the transaction to functional exchange rate that is indicated for the subcontract PO in the Exchange Rates subtask of the Enter POs screen.
These fields default from the main screen. These fields were originally established in the Enter POs screen.
This field displays the PO total amount, or the sum of the Ext Cost Amount fields (in the Enter POs screen), as it currently appears for the PO.
If you have generated change orders against the PO, this field displays the PO's current total value (for the change order) less the original total value of the PO.
If you have generated change orders against the PO, this field displays the PO Total (i.e., the sum of the Ext Cost Amount fields in the Enter POs screen).
This field displays the sum of the Requested Work Amount values for all PO lines in the main screen table window.
This field displays the sum of the Completed Work Amount values for all PO lines in the main screen table window.
This field displays the sum of the Stored Materials Amt values for all PO lines in the main screen table window.
This field displays the sum of the Completed Work Retention Amt values for all PO lines in the main screen table window.
This field displays the sum of the Stored Materials Retention Amt values for all PO lines in the main screen table window.
This field is calculated as the sum of Total Completed Work Amt + Total Stored Materials Amt - Total Completed Work Retention Amt - Total Stored Materials Retention Amt for all PO lines.
This field displays the sum of the Prev Vouchered Amount values for all PO lines in the main screen table window.
This field displays the sum of the Eligible for Voucher Amt values for all PO lines in the main screen table window. This is equal to Total Earned Less Retention Amt - Total Previously Vouchered Amt.
This field is calculated as the sum of Subcontract Order Amount - Total Completed Work Amt - Total Stored Materials Amt for all PO lines.
This field is calculated as the sum of Subcontract Order Amount - Total Completed Work Amt - Total Stored Materials Amt + Total Completed Work Retention Amt + Total Stored Materials Retention Amt for all PO lines.
This field displays the sum of the Sales Tax/VAT Amount Payable values for all PO lines in this progress payment request.