Use this subtask to view project labor grouped by the PLC charged. Employee timesheet detail is posted to the Labor History table as part of the Labor Distribution posting. The process that creates the report table for the Labor Summary Report summarizes this information by project, fiscal year, period, subperiod, and PLC.
Because data displayed in this table window is from the Project Labor Summary Report table, you must create that table for the project and subperiod needed before using the inquiry.
This non-editable field displays the fiscal year that you entered when you created the project report table.
This non-editable field displays the period that you entered when you created the project report table.
This non-editable field displays the subperiod that you entered when you created the project report table.
This non-editable field displays the rate type from the main screen.
This non-editable field displays either the owning or performing organization of the project depending on the selection made on the main screen.
This non-editable field displays a project number for the project. The project name displays in the field to the right.
This non-editable field displays the period of performance for the project.
This non-editable field displays the customer name for the project.
These non-editable fields display the contract value for the project.
This non-editable field displays the cost portion of the contract value for this project.
This non-editable field displays the fee portion of the contract value for this project.
This non-editable field displays the total contract value for this project.
The labor summary table window summarizes labor charges for the project, organization, and subperiod selected by PLC. The table window displays current subperiod, period-to-date, Year-to-Date (YTD), and Inception-to-Date (ITD) hours and amounts charged to each PLC. The current subperiod and period are those you selected, and are carried forward from the main screen. The YTD and ITD fields are as of the subperiod selected.
Click this button to view employee detail for the selected PLC. This detail is also stored in the Project Labor Summary report table.
These non-editable fields display the hours by subperiod, period, YTD, and ITD for the Project Labor Category.
These non-editable fields display the amount by subperiod, period, YTD, and ITD for the Project Labor Category.