PART LEAD TIME

Use this subtask to make selections that will calculate the total lead time for this part. Use it when you initialize your planning data or when making additions or changes to the part.

Part, Rev, U/M, Make/Buy

The Part, Rev, U/M, Make/Buy Status of "M" or "B," and Part Description information from the Planning Part Data screen are displayed.

Total Lead Time

The Total Lead Time that is calculated will be displayed. It is the total number of days for all lead time types selected. This total will be updated when changes are made to the selected lead time types. This is a display-only field and cannot be changed.

Lead Time Type

Description

This column displays system-defined lead time types.

Select/Deselect

Highlight a lead time type and click on the Select pushbutton. The lead time type that you selected will move to the Selected Lead Time group box, where it will be used to calculate the total lead time. To deselect, highlight the lead time in the Selected Lead Time group box and click on the Deselect pushbutton. The highlighted lead time will move back to the Lead Time Type group box.

Selected Lead Time

Description

This column displays the lead time types that you selected using the Select pushbutton.

Days

Enter the number of days required to process the part for each lead time type that has been selected.