MASTER PRODUCTION SCHEDULE DATA

This subtask is only available if you have a license for the Master Production Scheduling module.  The fields display data as set up in the Master Production Scheduling (Materials » Master Production Scheduling) module.

Part

This field displays the part number for the part selected on the main screen. The description of the part displays in the field below this one.

Rev

This field displays the revision number for the selected part.

U/M

The inventory, or default unit of measure for the selected part displays in this field.

Make/Buy

This field displays M (Make) or B (Buy), depending on whether the part is typically manufactured or purchased.

Total Lead Time

This field displays the total lead time, in days, for the part as specified in the Planning Part Data (Materials » Product Definition » Part Master) screen.

Planning Type

This field displays the planning type for this part:

Master Production Scheduling Time Fence (Days)

The MPS time fence is intended to limit changes to the master production schedule within a specified amount of time in the future.

This value in this field is used as the MPS time fence only if the MPS Time Fence Method field on the MPS Settings (Materials » Master Production Scheduling » MPS Controls) screen is set to Use Part Time Fence.

Sales Order Time Fence (Days)

Enter a value in this field to limit changes to the sales order within a specified amount of time in the future.

Cumulative End Part Lead Time (Days)

Enter a value in this field to define the total lead time, including component and subassembly lead times, required to complete this part.

This value in this field is used as the MPS time fence only if the MPS Time Fence Method field on the MPS Settings (Materials » Master Production Scheduling » MPS Controls) screen is set to Use Part Cumulative Lead Time.