PART LEAD TIME

Use this subtask to make selections that will calculate the total lead time for this part. Use it when initializing planning data or when making additions or changes to the part.

Part, Rev, U/M, Make/Buy

The Part, Rev, U/M, Make/Buy status, and part Description information from the Planning Part Data screen are displayed.

Total Lead Time

This non-editable field displays the calculated total lead time. The system derives this value by adding the total number of days for all lead time types selected. This total will be updated when you make changes to the selected lead time types.

Lead Time Type

Description

This column displays system-defined lead time types.

Select/Deselect

Highlight the lead time type that you want and click on the Select pushbutton. The lead time type that you selected will move to the Selected Lead Time group box, where it will be used to calculate the total lead time. To deselect, highlight the lead time that you want and click on the Deselect pushbutton. The highlighted selected lead time will move back to the Lead Time Type group box.

Selected Lead Time

Description

This column displays the lead time types you selected using the Select pushbutton.

Days

Enter the number of days required to process the part for each lead time type selected.