PRODUCTION CONTROL SETTINGS

Use this screen to establish control parameters and default data used throughout the module. Set up this screen when initializing Costpoint Production Control and maintain it whenever changes are needed to the control parameters.

MO Numbering Method

Manufacturing order numbers can contain a maximum of 10 characters.

Manual

Select this option to manually enter the manufacturing order ID.

Warehouse

Select this option to have the system assign a manufacturing order ID by warehouse. This is the system default. You must set up a last transaction ID (containing up to 10 alphanumeric characters) in the Transaction IDs subtask of the Warehouses (Materials » Inventory » Inventory Controls) screen before the system can generate a new manufacturing order ID, and the Auto-Assign field in the Transaction IDs subtask of the Warehouses screen must be set to Y. To have manufacturing order IDs generate in correct numeric order, you must select a ceiling number not to exceed 10 digits. For example, if the highest number desired is 9999999999, enter zero as 0000000000; or if the highest number desired is MO-9999, and the last ID used was MO-124, enter that number as MO-0124.

Project

Select this option to have the system assign a manufacturing order ID by inventory project. You must set up a Last MO ID (containing up to 10 alphanumeric characters) in the Inventory Projects (Materials » Inventory » Inventory Controls) screen before the system can generate a new manufacturing order ID. To have manufacturing order IDs generate in correct numeric order, you must select a ceiling number not to exceed 10 digits. For example, if the highest number desired is 9999999999, enter zero as 0000000000; or if the highest number desired is MO-9999, and the last ID used was MO-124, enter that number as MO-0124.

Default MO Status

Use this drop-down list to select the default MO status. The options are Planned, Firm Planned, or Released.  If you are using Costpoint Material Requirements Planning, the Planned option is not available.

Planner Assignment

There are several options available to assign the planning method. Select one option that best meets your requirements.

Part

Select this option if you want planners to be assigned work by specific part numbers. This is the system default.

Inventory Project

Select this option if you want planners to be assigned work by inventory projects.

Netting Group

Select this option if you want planners to be assigned work by project netting group.

Sales Order

This option is not available at this time.

Commodity

Select this option if you want planners to be assigned work by commodity code.

Product Classification

This option is not available at this time.

Date Effectivity Option

Use As-of Date for All

Select this option if the planned as-of date should be the effectivity date for all planned parts in a BOM.

Back Schedule Lead Time

This option is not available in this version of Costpoint.  However in future versions, select this option to back-schedule BOM effectivity dates based on planned cumulative part lead times.

Default Restrictions for Closed MOs

Allow Timesheet Charges

Select this check box to allow timesheet charges on newly closed MOs. This defaults the Allow Timesheet Charges flag on newly closed MOs to Y (Yes).

Allow Inventory Issues

Select this check box to allow material issues on newly closed MOs. This defaults the Allow Material Issues flag on newly closed MOs to Y (Yes).

Allow Subcontractor Charges

Select this check box to allow subcontractor charges on newly closed MOs. This defaults the Allow Subcontractor Charges flag on newly closed MOs to Y (Yes).

Backflush Timing

First Issue

Select this option to pull backflush parts from inventory upon the first issue to that MO. This is the system default.

Relief

Select this option to pull backflush parts from inventory upon MO relief.  Selecting this option enables the Autoload button in the Enter Manufacturing Order Issues (Materials » Inventory » Issues) screen.

Lead Time Calculation

Standard Calendar

Select this option to use the standard calendar when backscheduling requirements from lead time. This is the system default.

Shop Days

Select this option to use the shop calendar when backscheduling requirements from lead time.

Default Restrictions for Completed MOs

Allow Timesheet Charges

Select this check box to allow timesheet charges on newly completed MOs. This defaults the Allow Timesheet Charges flag on newly completed MOs to Y (Yes).

Allow Inventory Issues

Select this check box to allow inventory issues on newly completed MOs. This defaults the Allow Material Issues flag on newly completed MOs to Y (Yes).

Allow Subcontractor Charges

Select this check box to allow subcontractor charges on newly completed MOs. This defaults the Allow Subcontractor Charges flag on newly completed MOs to  Y (Yes).

Timesheet Entry Requirements

Operation Sequence Number

Select this check box to require users to enter routing sequence/step numbers on MO timesheets.

Work Center

Select this check box to require users to enter work centers on MO timesheets.

Allow Full Changes on MO Routing Lines

Select this check box to allow planners to change MO routing lines after they are copied from the standard routing table.

Allow Full Changes on MO BOM Components

Select this check box to allow planners to change MO requirement lines after they are copied from the BOM table.

Allow Multiple Inv Abbrev Build-To Allocations for MOs

Select this check box to allow MO build quantities to be split to multiple inventory abbreviations.

Allow MO for Unreleased Build Parts

Select this check box to allow MOs to be created for parts that are not yet released.

Allow MO to Use Unreleased Routings

Select this check box to allow unreleased routings to be copied to a MO.

Allow Auto-Update MO status In-Shop

Select this check box to have the MO status updated to In-Shop when a timesheet is charged to it.

Set Reservation ID to MO Number

Select this check box to have the ID of a MO's reservation set to the MO ID.

Load Capacity Planning Routing Lines to MO

Select this check box to auto-load capacity planning-only routing lines (where the Step Type is P for the routing line in the Maintain Routings and/or Release Routings (Materials » Routings » Routings) screens) to new manufacturing orders. Routing lines, which are assigned to MOs in the Routings subtask of the Enter Manufacturing Orders (Materials » Production Control » Manufacturing Orders) screen, can be automatically loaded in the subtask if they exist for the Build Part. However, if you clear this check box and attempt to auto-load routing lines in the Routings subtask of the Enter Manufacturing Orders screen, capacity planning-only routing lines are excluded from the table window. This check box's setting is also used by the Download Manufacturing Orders application (in the Advanced Planning and Scheduling menu in Product Interfaces (Others » Product Interfaces)) to determine how MO data is downloaded.

Default Common Stock Inv Abbrev

Enter, or use to select, the inventory abbreviation that should be used as the default common stock inventory abbreviation for planning.

Display Charging Employee Names

Select this check box to display charging employee name/ID on the timesheet section of the MO status inquiry.

Incl MRB as Available Inventory

Select this check box to include MRB inventory as available inventory for planning.

Incl Scrap/Yield % in MO Requirements

Select this check box to include planned scrap and yield quantities on MO requirements and pick lists.

Incl Scrap/Yield % in Planning Process

Select this check box to include planned scrap/yield quantities when calculating requisition/order quantities during planning.

Validate Reliefs Against MO QC Acceptance

Use this drop-down list to limit the ability to relieve an MO when total MO relieved quantity exceeds accepted quantity for one or more QC inspection routing steps (as specified in the MO Routing table). This provides an additional control to ensure that only parts that have passed inspection are moved back into inventory.

This allows you to specify, at the company-level, how you want this validation performed. Your choices are:

Validate MO Completions Against Open Requirements

Use this drop-down list to limit the ability to complete a Manufacturing Order when there are open requirements. This provides an additional control to ensure that relieved parts are costed correctly and that component inventory is properly issued.

This allows you to specify, at the company-level, how you want this validation performed. Your choices are:

Table Information