Use this subtask to view inventory cost element information for the selected transaction line.
When creating an inventory transaction line for any MO Relief, the lower level unit costs for each cost element are calculated from the lower level relieved costs included in the unit price of a relief line. The calculation is based on the percentage of lower level costs that make up the total costs for a cost element on an MO. You should include this amount on the inventory transaction line in the new lower level cost amount columns. These amounts will be copied if the transaction is cloned and reversed.
If the Build To project (in the Allocations subtask of the Enter Manufacturing Orders screen) has a costing method of "S" (Standard), the cost of all quantity reliefs is determined by the standard costs for the build to part in the Maintain Item Costs screen or Maintain Project Item Costs screen in Product Definition.
This field displays the ID of the manufacturing order.
This field displays the status of the MO.
This field displays the cost type being used.
This field displays the ID of the build part. A description of the part displays in the untitled field below this field.
This field displays the revision level of the build part.
This field displays the unit of measure of the build part.
The direct material total cost displays in this field.
The direct labor total cost displays in this field.
This field displays the direct subcontract total cost.
This field displays the direct miscellaneous 1 total cost.
This field displays the direct miscellaneous 2 total cost.
This field displays the direct total cost.
This field displays the total number of labor hours spent on this MO.
This field displays the burden material total cost.
This field displays the burden labor total cost.
This field displays the burden subcontract total cost.
The burden miscellaneous 1 total cost is displayed in this field.
The burden miscellaneous 2 total cost is displayed in this field.
The burden total cost is displayed in this field.
The direct material relieved cost displays in this field.
This field displays the direct labor relieved cost.
This field displays the direct subcontract relieved cost.
This field displays the direct miscellaneous 1 relieved cost.
This field displays the direct miscellaneous 2 relieved cost.
This field displays the direct relieved total cost.
This field displays the burden material relieved cost.
This field displays the burden labor relieved cost.
The burden subcontract relieved cost displays in this field.
The burden miscellaneous 1 relieved cost displays in this field.
The burden miscellaneous 2 relieved cost displays in this field.
The burden relieved total cost displays in this field.