COST ELEMENTS

Use this subtask to derive the unit cost of a part. The unit cost can be broken down into various direct and burden elements such as material, labor, subcontract, and miscellaneous. If Cost Suppression is active (the Suppress Cost checkbox is selected in the table window of the Maintain Users screen in Costpoint System Administration), this subtask is disabled.

Access this subtask whenever a unit cost should be attached to the part that has been adjusted.

Part, Rev, Project, Cost Method

The part, revision, part description, project, project description, and cost method are displayed in these non-editable fields.

Direct Cost Elements

If you have entered the From Inv Abbrev in the main screen table window, the fields in the Direct Cost Elements group box will be enabled.  Otherwise, these fields will be non-editable.

Material

Enter the direct material unit cost.

Labor

Enter the direct labor unit cost.

Subcontract

Enter the direct subcontract unit cost.

Misc 1

Enter the direct miscellaneous 1 unit cost.

Misc 2

Enter the direct miscellaneous 2 unit cost.

Burden Cost Elements

The fields in this group box are non-editable.

Material

This field displays the burden material unit cost.

Labor

This field displays the burden labor unit cost.

Subcontract

This field displays the burden subcontract unit cost.

Misc 1

This field displays the burden miscellaneous 1 unit cost.

Misc 2

This field displays the burden miscellaneous 2 unit cost.

Total Unit Cost

The total of all cost elements entered is displayed as the total unit cost for this part.