Use this screen to enter the days per period that you would like to use to spread budgeted data. This screen is used in conjunction with the Spread Budgets Based on Days check box in the Maintain Project Budget Settings screen (Projects » Advanced Project Budgeting » Controls). If you did not select the check box, you can enter data in this screen, but it will not be used. The intent of this screen is to enable you to spread budget data by month based on the number of days in each month. The selection in the Maintain Project Budget Settings screen is a system-wide selection.
You should populate this screen before entering budgets in the Maintain Project Budgets and ETC screen (Projects » Advanced Project Budgeting » Project Budget and ETC Master). The system will use the days per period in this screen when you use the "spread" function in the subtasks of the Maintain Project Budgets and ETC screen. The amounts will be spread over the periods based on the weighted number of days in the period.
Enter, or use to select, the fiscal year in this column. The fiscal year entered here must already be set up in the Fiscal Years screen in Costpoint General Ledger.
Enter, or use to select, the period in this column. The period entered here must already be set up in the Accounting Period screen in Costpoint General Ledger.
Enter the number of days in the period in this screen. This number will be used to calculate the amount per period.
Click this button to load the fiscal year and period information from the Fiscal Years (Accounting » General Ledger » Controls) and Accounting Periods (Accounting » General Ledger » Controls) screens. All fiscal years and periods that exist in the screens will be loaded when this option is used.
Changes to this screen update the PROJ_BUDGET_DAYS table.