Actual Costs Preferences
Use this dialog box to select the options for loading actual costs for a project.
Contents
| Field | Description |
|---|---|
| Allow posting actual costs to a planned Control Account or Work Package | When you select this option, Cobra will allow actual costs to be entered against a control account or work package that has a status of Planned. Planned control accounts or work packages do not have an actual start date.
|
| Allow posting actual costs to a completed Control Account or Work Package | When you select this option, Cobra will allow entry of actual costs against control accounts or work packages with a status of Complete. When you clear this option, Cobra will load actuals for completed control accounts and work packages only if their actual finish date falls within the last period date and the current status date. Subsequently, Cobra will list the completed control accounts and work packages that have their finish date before the current period date as errors in the process log. |
| Prevent loading historical actual cost | When you select this option, Cobra will allow loading of the actual costs only with cost date values that fall between the start and finish dates of the current status period during the Actual Cost Integration process. By default, this option is not selected. This option applies only if you select Period Costs on the Included Costs page of the Integration Wizard. |
| Auto-create missing Control Account or Work Package | When you select this option, Cobra will enable the automatic creation of non-existing control accounts and work packages during the Actual Cost Integration process.
|
How to...
Learn more about...
Options Page of the Integration Wizard-Actuals
File Selection Page of the Integration Wizard-Actuals
Integration Wizard-Actual Costs
Automatic Creation of Control Accounts and Work Packages