Freeze Forecast Process

Use the Freeze Forecast process to freeze a forecast and retain historical forecast data

Process Settings

Below are the settings you must define for the Freeze Forecast process.

Setting Description Sample Value
ProcessIDThis setting informs Cobra to run the Freeze Forecast process. FreezeForecast
ProjectThis setting refers to the project for which you want to run the Freeze Forecast process.

The project name is case-sensitive. This setting is required.

Demo Advanced
CriteriaUse this setting to choose the selection criterion you want to use for the Freeze Forecast process. The selection criteria changes based on the project.

Use one of the following values for this setting:

  • Total Project
  • Control Account
  • Work Package

This setting is optional and the default value is Total Project.

Total Project
SelectionUse this setting to specify the portion of the project for the Freeze Forecast process. The available values are based on the value you specify for the Criteria setting.

If you specify Total Project in the Criteria setting, the Selection setting will be left blank.

This setting is optional and has no default value.

1.1.1.2 / 1420,1.1.2.1 / 1600
ForecastCostSetUse this setting to specify the cost set that contains the classes whose values will be copied to the Frozen Forecast class.

This setting is required.

EAC
FrozenForecastClassUse this setting to specify the Frozen Forecast class to which the values from the cost set classes—specified in the ForecastCostSet setting—will be copied. FF

Sample Script

Below is a sample script file for the Freeze Forecast API process.

[PROCESS000]
ProcessId=FreezeForecast
Project=Demo Advanced
Criteria=Control Account
Selection=1.1.1.2 / 1420,1.1.2.1 / 1600
ForecastCostSet=EAC
FrozenForecastClass=FF