Codes and Structures Page of the Cost Data Wizard
Use this page to select the control account and work package code assignments and associated structures to be exported.
Control Account Tab or Work Package Tab
Use this tab to select the control account and/or work package code assignments to be exported.
Click the Control Account tab to display control account code assignments 1-20 defined on the selected project, regardless of code field type.
Click the Work Package tab to display work package code assignments 1-20 defined on the selected project, regardless of code field type.
Note:
- This page displays the information specified on the Control Account Codes tab or on the Work Package Codes tab of the Fields tab of the Project Properties dialog box for the selected Cobra project.
- Codes used to map the WBS and OBS fields on the Export Structures page may not be selected again on this page.
- When you export at the control account level, IsSummaryLevelPlanningPackage is always set to false. When you export at the work package level, if all work packages under the control account use the Planning Package progress technique, IsSummaryLevelPlanningPackage in WorkPackages.json is set to true. Otherwise, it is set to false.
- This page does not display if you select DOE PARS on the Project and Format page.
| Field | Description |
|---|---|
| Number | This field displays the location of the codes on the control account or work package. |
| Prompt | This field displays the user prompt for each code field. |
| Code File | This field displays the names of the code files. This checkbox is blank if the code field type is not Code (optional) or Code (required). |
| Export Value | Select this checkbox to export the value assigned to the control account or work package code. By default, this checkbox is not selected. |
| Export Structure | Select this checkbox to export the associated code file structure. This checkbox is available only when exporting the DCDE format. By default, this checkbox is not selected. If you select Deltek Common Data on the Project and Format page, take note of the following:
If you select IPMDAR-Contract Performance Format on the Project and Format page, take note of the following:
|
| Custom Summary | Select this checkbox to include either the control account code file or the work package code file in the CustomSummaryPerformance.json file during the IPMDAR CPD export. This checkbox is available only when exporting the IPMDAR format. By default, this checkbox is not selected. |
Parent Topic: Cost Data Wizard