Update EAC Dialog Box

Use this dialog box to manually update the forecast values for a control account or work package.

If you selected Currency or Hours in the Scale Retain EAC field of the Forecast section of the Preferences Tab of the Project Properties dialog box, the Update EAC dialog box contains a field for updating the value for the Hours or Currency. If you selected Hours and Currency in the Scale Retain EAC field, the Update EAC dialog box contains two fields for updating the values for both the Hours and Currency.

You can use the Update EAC utility only if you selected Hours, Currency, or Hours and Currency in the Forecast section of the Preferences tab of the Project Properties dialog box.

You must have access control that is greater than read-only to use the Update EAC utility.

Contents

Field Description
Old value

This field displays the old value for the Hours or Currency. You cannot change the value in this field.

New value

Enter the new value for the Hours or Currency in this field.