Synchronize Status Dates

When you create a new project, the status date is set equal to the date labeled TODATE in the calendar. However, if TODATE is not properly labeled at project creation time, you can use the Synchronize button on the General tab of the Project Properties dialog box to change the status date without advancing the calendar.

Note: This option does not have all the functionality of advancing the calendar and should not be used as an alternative to the advance calendar function once the project is underway.

To synchronize status dates, complete the following steps:

  1. Display the Project Properties dialog box and select the Contract Information tab.
  2. Click Synchronize.
  3. Click Apply to save the changes.