Resource Assignments
Cobra project costs are entered as resource assignments. The list of resources that you can add are defined in the resource file. The resource file used for a project is defined on the Files tab of the Project Properties dialog box.
When you add a resource assignment to either a control account or work package, you select a resource from the resource file assigned to the project. Then you choose the class. By default, you can select from either Budget or Forecast, but you can define an unlimited number of classes in Cobra.
You then choose the result you want to enter the value of. The list of results are defined in the calculation of the resource. Typically, you will enter the value in hours for labor and direct for material costs.
After entering the value, you choose a spread curve. The curve will define how the value is spread over the control account or work package dates to create time-phase data.
- Time-phase pane of the Project view
- Time-phase Detail pane of the Project view
- Related Topics:
- Add Resource Assignment Dialog Box
Use this dialog box to add new work assignments to a control account or work package.