Assign a Rolling Wave Calendar to the Project
Use the Project Properties dialog box to assign a rolling wave calendar to the project.
To assign rolling wave calendar to a project, complete the following steps:
- Display the Project Properties dialog box and select the Files tab.
- In the Rolling Wave group box, select the rolling wave calendar in the Calendar field.
- Click Apply and OK.
How to...