Apportionment Mapping
One of the setup steps for apportionment is to link source control accounts with target control accounts.
After you have chosen a project for apportionment, use the Apportionment Mapping utility to add, edit, or delete apportionment sources and targets.
- Source — The project and control account where the budget for the apportionment calculations is located.
- Target — The project , control account, and/or work package where the data will be created.
The Apportionment Mapping dialog box has two sections: the Apportionment Target pane and the Apportionment Source pane. Use the Apportionment Target pane to specify the project and account where the apportioned resource will go and the rate that will be used in apportionment calculations. Use the Apportionment Source pane to select the project and control account where the budget for the apportionment calculations are located.
Apportionment Mapping can be defined at the project or master project level. If apportionment is defined at the master project level, it is possible to apportion to any subproject that belongs to the master project.
- Related Topics:
- Apportionment Dialog Box
Use this dialog box to create budget, earned value, and forecast for work that is based on other work. - Apportionment Mapping Dialog Box
Use this dialog box to link source control accounts with target control accounts. You can also use this dialog box to calculate the apportioned resources defined in the target control accounts based on the resources used in the source control accounts. - Add Apportionment Target Dialog Box
Use this dialog box to define where the apportionment data will be created. - Add Apportionment Source Dialog Box
Use this dialog box to define where the budget for the apportionment calculations is located. - Procedures