Use the Project Selection page of the Integration wizard to select the files from which you will import data, and the Cobra project where data is imported to.
Contents
Field | Description |
Activity File
|
Click
to select the activity file that contains information on control accounts and work packages. The data required in this field depends on the option you select on the Action Selection page.
Note: You must select an activity file when importing any type of data except
Status data.
|
Resource Assignment File
|
Click
to select a resource assignment file to import.
This field is required when you select
Resource Assignments on the Action Selection page.
|
Use one file with activity and resource assignment data
|
Select this check box to import budget from a single budget file that contains both activity and resource data. Selecting this check box enables the
Activity and Resource Assignment File field and disables the
Activity File and
Resource Assignment File fields.
This check box is not selected by default.
|
Activity and Resource Assignment File
|
Click to select the file that contains both the activity and resource assignment data. This field becomes enabled only if you select the
Use one file with activity and resource assignment data check box.
When there are two or more records that represent different resource assignments belonging to the same activity, Cobra imports the activity information from the first record in the file.
|
Status File
|
Click
to select a status file you want to import.
Note: This field is required when you select
Status on the Action Selection page.
|
Cobra Project
|
Click
to select the Cobra project where data is imported to. You can also enter the name of the project. However, ensure that the project is valid and that you have write permissions to it.
|