Specify the Analysis Period

Initially, the Historical Pipeline Analytics display historical pipeline data since the installation of Capture Analytics.

You can use the calendar bars across the top of the tab to change the analysis period reflected in the charts and tables on the Historical Pipeline tab.

Basics_AnalysisPeriodComplete.png

If you make selections, Capture Analytics updates the analytics based on the weekly or monthly historical pipeline data for the modified analysis period.

You can also change the analysis period by selecting one or a more bars on the Historical Pipeline Comparison chart or by selecting one or a range of dates in one of the tables.

The analysis period you specify on the Historical Pipeline tab only applies to the analytics on that tab.

Available Analysis Period

As part of Capture Analytics configuration, your system administrator specifies whether your firm wants to analyze changes in pipeline on a weekly or monthly basis.

How many weeks or months are available for analysis depends on how long your firm has been using Capture Analytics.

You may have some historical pipeline data immediately available when you begin using Capture Analytics. Capture Analytics includes the capability to begin capturing pipeline changes in GovWin Capture Management as soon as the workflow process is installed. If your firm takes advantage of that option, limited historical pipeline data may be available the day you begin using Capture Analytics.

Analyze Data for Calendar Years

Basics_AnalysisPeriodYear1.png

Basics_AnalysisPeriodYear2.png

To select one calendar year, click that year.

To select more than one year, do either of the following:

  • Click the first year, hold down the mouse button, and drag the mouse pointer over the other years.

  • Click the first year, and then press CTRL as you click each of the other years.

Analyze Data for Selected Calendar Quarters

Basics_AnalysisPeriodQuarter.png

  1. Select the calendar year or years.

  2. To select one quarter, click that quarter.

To select more than one quarter, do either of the following:

  • Click the first quarter, hold down the mouse button, and drag the mouse pointer over the other quarters.

  • Click the first quarter, and then press CTRL as you click each of the other quarters.

Analyze Data for Selected Months

Basics_AnalysisPeriodPeriod.png

  1. Select the calendar year or years.

  2. To select one month, click that month.

To select more than one month, do either of the following:

  • Click the first month, hold down the mouse button, and drag the mouse pointer over the other months.

  • Click the first month, and then press CTRL as you click each of the other