Budgeting & Planning provides the following types of task status.
Milestones – a drop-down list and associated legend provide appropriate choices.
Percent complete – direct input as xx.x (25.2%).
Percent complete constrained by milestone gates – dual input consisting of direct input as xx.x (25.2%) and a drop-down list and associated legend provide necessary secondary choices.
Equivalent units/standards – direct input of a whole number where a legend provides total units at completion.
Apportioned – input not allowed.
Level-of-effort – input not allowed.
After each lowest level project status has been updated, a Budgeting & Planning EVM database table re-calculation process can be initiated from the status page.