You are here: Ajera Help (A-Z) > projects > project setup > Copying a phase

Copying a phase

To copy a phase

  1. With the project open in the Project Command Center window, in the project tree on the bottom left of the window, click the phase you want to copy.
  2. Click Copy.
  3. Click Yes to copy the phase.
  4. Change the description. If you are using IDs, also change the ID.
  5. Make any other changes.
  6. Click Save.

 

 