Actual Cost / ACWP (AC)
|
Collect the following data:
- Resource Units (sum of the act_reg_qty and the act_ot_qty of the activity's resource assignments)
- Actual Labor Units (the activity's value for act_work_qty x 60)
- Actual Non-labor Units (activities value for act_equip_qty)
Using the information above, find the rounded-off value (ceiling) using the following formula: (Actual Labor Units / 60) + Actual Non-Labor Units - Resource Units
The Actual Cost of the activity is calculated using the following formula:
SUM(Resource Assignments Actual Costs) + SUM(Project Expenses Actual Costs) + (<rounded off value that you calculated above> x def_cost_per_qty)
|
Actual Duration
|
- If act_start_date is empty, then value is
0.
- If last_recalc_date is empty, then value is
0.
- If the activity has a calendar, use the calendar to convert the difference between the activity's act_end_date and the act_start_date to the correct duration units. If act_end_date is blank, then use
last_recalc_date.
- If the activity does not have a calendar, use the total number of minutes difference between the activity's act_end_date and the act_start_date. If act_end_date is blank, use last_calc_date.
|
At Completion Duration
|
- Actual Duration + (the activities remain_drtn_hr_cnt x 60)
|
Budget Cost
|
Collect the following data:
- Resource Units (sum of the resource assignments target_cost)
- Budgeted Labor Units (value of the activity's target_equip_qty)
- Budgeted Non-labor Units (value of the activity's target_equip_qty)
Using the information above, find the rounded-off value (ceiling) using the following formula: (Budgeted Labor Units / 60) + Budgeted Non-Labor Units - Resource Units
The Budget Cost of the activity is calculated using the following formula:
SUM(Resource Assignments'"target_cost") + SUM(Project Expenses target_cost) + (<rounded off value that you calculated above> x def_cost_per_qty)
|
Baseline Cost
|
- If the project has a baseline: Actual Cost + Remaining Cost
- If the project does not have a baseline, use Budget Cost
|
Baseline Duration
|
- If the project has a baseline: get the
baseline
activity's budget duration value from: target_drtn_hr_cnt x 60
- If the project does not have a baseline, get the
current
activity's budget duration from: target_drtn_hr_cnt x 60
|
Baseline Finish
|
- If the project has a baseline: use the baseline activities Finish Date
- If the project does not have a baseline, use the current activity's value for target_end_date
|
Baseline Start
|
- If the project has a baseline: use the baseline activities Start Date
- If the project does not have a baseline, use the current activity's value for target_start_date
|
Baseline Work
|
- If the project has a baseline: act_work_qty + remain_work_qty
- If the project does not have a baseline, use the current activity's target_work_qty x 60
|
Percent Complete
|
- If complete_pct_type has a vlue of
CP_Phys, then the value is
Phys_complete_pct
- If complete_pct_type has a value of
CP_Drtn, then the value is
Duration Percent Complete which is calculated as follows:
- If activity status is
Planned, then the value is
0
- If activity status is
Complete, then the value is
100
- If activity status is In
Progress, then:
|
BCWP (EV)
|
(Baseline Cost) * (Percent Complete / 100)
See Baseline Cost and Percent Complete rows above for their respective formulas.
|
BCWS (PV)
|
|
Critical Flag
|
- If act_end_date is not empty, or total_float_hr_cnt is empty, or task_type is TT_LOE, then the value is
False.
- If critical_path_type is set to
CT_TotFloat, and total_float_hr_cnt is less than or equal to the value of (critical_drtn_hr_cnt x 60), then the value is
True, otherwise the value is
False.
|
Duration Percent Complete
|
|
Remaining Cost
|
Collect the following data:
- Resource Units (sum of the activity's resource assignments remain_qty)
- Remaining Labor Units (value of the activity's remain_work_qty x 60)
- Remaining Non-labor Units (value of the activity's remain_equip_qty)
Using the information above, find the rounded-off value (ceiling) using the following formula: (Remaining Labor Units / 60) + Remaining Non-Labor Units - Resource Units
The Remaining Cost of the activity is calculated using the following formula:
SUM(Resource Assignments' Remaining Costs) + SUM(Project Expenses' Remaining Costs) + (value in (d) times "def_cost_per_qty")
|
EAC / Total Cost
|
- Actual Cost + Remaining Cost
See
Actual Cost
and
Remaining Cost
rows above for their respective formulas.
|
Earned Value Technique
|
- If the activity does not have a WBS, then the value is empty.
- If WBS' EVT value is
EC_MS, then the value is
Milestone.
- If WBS' EVT value is
EC_Cmp_pct, then the value is
Percent Complete.
- If WBS' EVT value is
EC_50_pct, then the value is
Fifty Fifty.
- If WBS' EVT value is
EC_0_pct, then the value is
Zero Hundred.
- If WBS' EVT value is
EC_User_pct, then the value is
User Defined.
- If none of the above apply, then the value is
Percent Complete.
|
Earned Value Work
|
- (Baseline Work x Percent Complete) / 100
See
Baseline Work
and
Percent Complete
rows above for their respective formulas.
|
Finish Date
|
- If act_end_date is not empty, then the value is
act_end_date.
- If act_end_date is empty, then the value is
target_end_date.
|
Start Date
|
- If act_start_date is not empty, then the value is
act_start_date.
- If act_start_date is empty, then the value is
target_start_date.
|
Is Level of Effort
|
- If remain_drtn_hr_cntis
0, then the value is
True, otherwise the value is
False.
|
Remaining Duration Elapsed
|
- If task_type is
Level of Effort, then the value is
True, otherwise the value is
False.
|
Maximum Lag
|
- Largest value of Lag from the activity's list of successors.
|
Minimum Lag
|
- Smallest value of Lag from the activity's list of successors.
|
Number of FS Predecessors
|
- Find the number of activity predecessors that have a link type of
Finish to Start.
|
Number of FS Successors
|
- Find the number of activity successors that have a link type of
Finish to Start.
|
Number of SS Predecessors
|
- Find the number of activity predecessors that have a link type of
Start to Start.
|
Number of SS Successors
|
- Find the number of activity successors that have a link type of
Start to Start.
|
Number of SF Predecessors
|
- Find the number of activity predecessors that have a link type of
Start to Finish.
|
Number of SF Successors
|
- Find the number of activity successors that have a link type of
Start to Finish.
|
Number of FF Predecessors
|
- Find the number of activity predecessors that have a link type of
Finish to Finish.
|
Number of FF Successors
|
- Find the number of activity successors that have a link type of
Finish to Finish.
|
Number of Lags
|
- Find the number of activity predecessors that have a positive value of
Lag.
|
Number of Leads
|
- Find the number of activity predecessors that have a negative value of
Lag.
|
Number of Predecessors
|
- Find the number of activity predecessors.
|
Number of Successors
|
- Find the number of activity successors.
|
Planned Value Work
|
|
Status Date
|
- If last_recalc_date is empty, then the value is
plan_start_date.
- If last_recalc_date is earlier than plan_start_date, then the value is
plan_start_date.
- If neither of the above is true, then the value is last_recalc_date; however, if there is an activity in the project with the Start date that is earlier than the above values, then the value for the Status Date is the earliest activity's
Start Date.
|
Remaining Earned Work
|
- (Baseline Work)*[(100-Percent Complete)/100]
See the
Baseline Work
and
Percent Complete
lines above for their respective formulas.
|
Schedule % Complete
|
- If the current activity's
Baseline Start,
Baseline Finish, or
Project Time Now
is empty, or if
Baseline Start
is later than or the same as
Project Time Now, then the value is
0.
- If the current activity's
Baseline Finish is earlier than or the same as the
Project Time Now, then the value is
1.
- If the current activity does not have a calendar, then:
- Dividend = number of ticks between the
Project Time Now
and the
Baseline Start Date.
- Divisor = number of ticks between the
Baseline Finish Date
and
Baseline Start Date.
- If the current activity does have a calendar, then:
- Dividend = difference between the
Project Time Now
and the
Baseline Start Date
in the correct working units.
- Divisor = difference between the
Baseline Finish Date
and
Baseline Start Date
in the correct working units.
- If the Divisor is
0, then the value is
1.
- If the Divisor is not
0, then the value is calculated as follows:
("Dividend" / "Divisor")
|
Start Percentage
|
- If the activity does not have a WBS, then the value is empty; otherwise, value is
WBS.
|
Total Duration
|
- act_drtn_hr_cnt + (remain_drtn_hr_cnt x 60)
|
Total Work
|
- (act_work_qty + remain_work_qty) x 60
|
Units Percent Complete
|
|
WBS
|
- If the activity as a WBS, then the value is the WBS' generated GUID.
|
WBS Code
|
- If the WBS has a parent node (parent_wbs_id), then the value is calculated as follows: Parent Path.wbs_short_name
where
Parent Path
follows the same format as above (Parent Path.wbs_short_name).
|
CPI-Labor Units
|
- (Earned Value Work) / (act_work_qty * 60)
See the
Earned Value Work line above for its formula.
|
SPI-Labor Units
|
- (Earned Value Work) / (Planned Value Work)
See the
Earned Value Work and
Planned Value Work lines above for their respective formulas.
|
Variance - BL Finish Date
|
- If
Finish Date is empty, then the value is empty.
- If the project has a baseline, calculate the time difference between the
Baseline Finish and the activity's
Finish Date using the activity calendar to convert the duration to the correct working units (if a calendar exists), or to the total number of minutes if the activity's calendar does not exist.
- If the project does not have a baseline, calculate the time difference between the activity's
target_end_date and the activity's
Finish Date using the activity calendar to convert the duration to the correct working units (if a calendar exists), or to the total number of minutes if the activity's calendar does not exist.
See the
Finish Date line above for its formula.
|
Variance - BL Start Date
|
- If
Start Date is empty, then the value is empty.
- If the project has a baseline, calculate the time difference between the
Baseline Start and the activity's
Start Date using the activity calendar to convert the duration to the correct working units (if a calendar exists), or to the total number of minutes if the activity's calendar does not exist.
- If the project does not have a baseline, calculate the time difference between the activity's
target_start_date and the activity's
Start Date using the activity calendar to convert the duration to the correct working units (if a calendar exists), or to the total number of minutes if the activity's calendar does not exist.
See the
Start Date line above for its formula.
|