Redundancy Index
The redundancy index analysis pinpoints redundant logic links within a schedule.
This enables you to generate and maintain clean schedules that don't contain redundant or overlapping logic.
Example of Redundancy Index Analysis
You have three activities (A, B, and C) in sequence with FS logic links. If the schedule in question has a logic link between Activity A and C, then this link is essentially redundant as Activities A and C are already logically tied through Activity B.