Lags and Leads Group on the S2 // Logic Tab
Use the commands in this group to display relationship links that are carrying positive and negative lags and leads.
Field | Description |
---|---|
Lags | This command displays only relationships with lags. This is often used to represent non-working time between activities. For example, time for concrete to cure. |
Leads | This command displays only relationships with leads. A lead is a negative lag. This is often used to adjust the successor start/end date relative to the logic link applied. It can result in the successor starting before the start of the predecessor. |