S4 // Acceleration Tab (Acumen 360)
Acumen 360 is a schedule remediation and acceleration product. You use it to accelerate or compress project schedules to meet faster completion deadlines or to get a delayed project back on track.
In addition, 360 can be used to hypothesize acceleration options or model potential delays.
Acumen 360 runs a CPM simulation running hundreds of iterations, progressively accelerating the project towards a defined goal using sets of user-definable criteria.
There are three acceleration options:
- Automatic, Goal-Based allows you to define the acceleration target and let Acumen 360 automatically generate the schedule scenario that meets that goal.
- Targeted allows you to define the acceleration goal and the criteria for acceleration (for example, accelerate construction activities by 50%).
- Interactive allows you to accelerate or decelerate individual activities or groups of activities using the duration calibration sliders.
The S4 // Acceleration tab includes a script library/editor and a step library/editor.
Run an Acceleration from the S1 // Projects Tab
In addition to running acceleration scenarios on the S4 // Acceleration tab, you can also run them from the S1 // Projects tab by clicking Accelerate Schedule in the S1 // Projects Scenario Generation menu.
- Accelerated Remaining Duration
- Accelerated Start
- Accelerated Finish
- Accelerated Total Float
- Accelerated Free Float
- Accelerated Script (the name of the script used to accelerate the schedule)
- Accelerated: This is a checkbox that is selected if any of the following occurred with the acceleration:
- Remaining duration was reduced
- Predecessor lag was reduced
- Successor lag was reduced
- Calendar changed
- Constraints were removed
You can also use the above fields in the Metrics tab for filters and formulas, and on the Metrics Define Columns tab and Detailed Report tab. You can use these fields to build metrics and run reports that look at the results of acceleration.
If you create an accelerated scenario, an Acceleration tab is added to the Activity Details pane for the scenario project.
- Related Topics:
- S4 // Acceleration Tab Procedures
Use these procedures when working with the S4 // Acceleration tab. - Ribbon Commands on the S4 // Acceleration Tab
Use the ribbon commands to perform such tasks as accelerate the schedule, apply, merge, and save script libraries, and create scripts and steps. - Automatic Goal-Based Acceleration
Use automatic goal-based acceleration to define the acceleration target and let Acumen 360 automatically generate the schedule scenario that meets that goal. - Targeted Acceleration
Use targeted acceleration to define the acceleration goal and the criteria for acceleration. - Interactive Acceleration
The interactive acceleration mode of Acumen 360 allows you to accelerate or decelerate activities and immediately view the impact on the rest of the schedule. - Analyzing the Acceleration Results
Analyze the newly created scenarios using any of the standard analysis features within Acumen including Forensics, timeline view, and the Fuse diagnostics view. - Publishing Scenarios
You can publish Acumen 360 scenarios to MS Project and Primavera.