Import absolute or percentage activity uncertainty values into Acumen.
To import uncertainty data into Acumen, complete the following steps:
-
Select the S3 // Risk tab.
-
In the Views group, click
.
-
In the Import / Publish group, click the
Excel down-arrow and select
Import Activity Uncertainty.
-
On the Open dialog box, select the spreadsheet and click
Open.
-
On the Import Activity Uncertainty dialog box, specify whether you want to import absolute or percentage values.
Option | Description |
---|
Absolute |
This option calculates percentage values after import. |
---|
Percentage |
This option calculates absolute values after import.
|
---|
Cancel |
This option cancels the import. |
---|
The data imports into Acumen and displays on the S3 // Risk tab in the Activity view. If there were any errors, a dialog displays listing details of each error. Rows with errors are not imported into Acumen.