Create a Risk-Adjusted Schedule Based on Risk Outputs
You can create a scenario based on any P-Value from the risk analysis. After creating the scenario, you can publish the risk-adjusted schedule back to the scheduling tool or use it as the basis for building a new risk model.
To create a risk-adjusted schedule based on risk outputs, complete the following steps:
- Select the S3 // Risk tab.
- With the project selected in the Projects pane, in the Analysis group, click Build Scenario.
- Select Scenario Based on Risk Outputs, then edit the P Schedule value if needed.
- In the Analysis group, click Run Risk Analysis.
Parent Topic: Risk-Adjusted Schedule Procedures