Resource Assignments Tab of the Activity Details Pane
This tab displays information about the assigned resources for the selected activity.
Click on a column header to sort by that column.
Resource
Field | Description |
---|---|
Name | This column displays the name of the resource assigned to the selected activity. |
Units
A unit is one man hour.
Field | Description |
---|---|
Planned | This column displays the total man hours that are planned for the activity. |
Planned / Hr. | This column displays the number of man hours per hour that are planned for the activity. |
Actual | This column displays the man hours that have already been used for the activity. |
Remaining | This column displays the remaining man hours for the activity. |
Remaining / Hr. | This column displays the remaining number of man hours per hour for the activity. |
Cost
Field | Description |
---|---|
Cost Based on Units | This check box indicates if the cost of the resource is based on the rate of the unit. If it is not selected, then the cost does not depend on the rate for the unit. |
Budget | This column displays the resource budget for the selected activity. |
Actual | This column displays the actual cost for the resource for the selected activity. |
Remaining | This column displays the remaining budget available to the resource for the selected activity. |
Parent Topic: Activity Details Pane