Cost Uncertainty Tab of the Activity Details Pane
This tab includes information about remaining cost, cost uncertainty, and risk notes.
Note: If you are working with duration uncertainty, then this tab is disabled.
Field | Description |
---|---|
Remaining Cost | This field displays the remaining cost for the selected item. |
Probability of Existence | This field displays the probability, in percentage, that a cost is going to happen in your project. If you are not 100% certain that a cost is going to happen in your schedule, you can assign a probability to reflect this confidence level. You can either enter a percentage in this field or in the % column on the S3 // Risk Activity grid. |
Risk Notes | Use this text box to enter any additional notes about the activity risks. These notes are only available for reference on this tab and the Duration Uncertainty tab. |
Parent Topic: Activity Details Pane