Cobra Status Tab of the Activity Details Pane
This tab displays the status that is specific to the control account or work package imported from Cobra.
Note: This tab does not display until you import cost data from a Cobra file ( ) and you select a control account or work package in the Activities grid.
Progress
Field | Description |
---|---|
Progress Technique | This field displays the earned value technique that Cobra uses to calculate earned value. Different methods are appropriate to different work packages, either due to the nature of the work or to the planned duration of the work package. It only displays when you select a work package in the grid.
If the Progress Technique is Milestone, the grid displays with milestones. |
Start Percent / Percent Complete | This field changes depending on the entry in the
Progress Technique field.
|
Status
Field | Description |
---|---|
Status | This field displays the status of the selected control account or work package (Planned, In Progress, or Complete. |
Baseline Start | This field displays the baseline start date that defines the initial planned start date for the control account or work package. |
Baseline Finish | This field displays the baseline finish date that defines the initial planned finish date of the control account or work package. |
Actual Start | This field displays the actual start date for the control account or work package. |
Actual Finish | This field displays the actual finish date for the control account or work package. |
Forecast Start | This field displays the forecast or estimated start date for the control account or work package. |
Forecast Finish | This field displays the forecast or estimated finish date for the control account or work package. |
Early Start | This field displays the early start date for the control account or work package. |
Early Finish | This field displays the early finish date for the control account or work package. |
Late Start | This field displays the late start date for the control account or work package. |
Late Finish | This field displays the late finish date for the control account or work package. |
Parent Topic: Activity Details Pane