Use the commands in this group to display different types of activity relationships.
Field/Option | Description |
All
|
Show all relationships together with total finish float and any associated lag.
|
Finish to Start
|
This displays only finish to start relationships. A logic link between the finish of the predecessor and the start of the successor. The successor cannot start until the predecessor is finished.
|
Finish to Finish
|
This displays only finish to finish relationships. A logic link between the finish of the predecessor and the finish of the successor. The successor cannot finish until the predecessor has finished.
|
Start to Finish
|
This displays only start to finish relationships. A logic link between the start of the predecessor and the finish of the successor. The successor cannot finish until the predecessor has started.
|
Start to Start
|
This displays only start to start relationships. A logic link between the start of the predecessor and the start of the successor. The successor cannot start until the predecessor has started. This often includes a lag.
|