This tab includes information about the script used, targeted goal, total acceleration, and a graphical representation of how the acceleration changes the project dates.
It displays when you accelerate the project by clicking
Accelerate Schedule in the Scenario Generation group on the S1 // Projects tab and adding the accelerated scenario to the project.
Field/Option | Description |
Script Used
|
This is the script that was used for the acceleration. You can add or edit scripts on the S4 // Acceleration tab.
|
Targeted Goal
|
This field displays the target date and whether the date is achieved with the accelerated schedule.
|
Total Acceleration
|
This field displays the number of days by which the project was reduced and the percentage by which the project was compressed to meet the goal.
|
Acceleration Bar
|
This bar displays the activity start and original end date as well as the acceleration goal date.
|