Standard Schedule Field Mappings

Acumen includes standard schedule field mappings for each of the supported platforms. You can create additional custom field mappings using the Fields tab.

Acumen Field IPMDAR Microsoft Project / Project Server Primavera P6 Primavera Risk Deltek Open Plan UN/CEFACT Safran Asta Powerproject

DOE PARS

Activity Status Calculated Status Activity Status Calculated Progress Type Calculated NA Status

Calculated

Activity Type TaskTypeID Calculated Activity Type Task Type Activity Type ProjectScheduleTask.TypeCode Calculated Type

TaskTypeID

Actual Cost NA Actual Cost Calculated Cost[Actual] Calculated NA Calculated ActualCost

NA

Actual Duration Calculated Actual Duration Actual Duration NA NA NA Calculated ActualDuration

Calculated

Actual Finish ActualFinishDate Actual Finish Actual Finish Actual Finish Actual Finish ActualScheduledBasePeriod. Finish Calculated ActualFinish

ActualFinishDate

Actual Start ActualStartDate Actual Start Actual Start Actual Start Actual Start ActualScheduledBasePeriod. Start Calculated ActualStart

ActualStartDate

ACWP (AC) NA ACWP ACWP NA NA NA

NA

Baseline Finish BaselineFinishDate Baseline Finish Planned Finish Baseline Finish Baseline Finish TargetScheduledBasePeriod. Finish Baseline Early Finish BaselineFinish

BaselineFinishDate

Baseline Start BaselineStartDate Baseline Start Planned Start Baseline Start Baseline Start TargetScheduledBasePeriod. Start Baseline Early Start BaselineStart

BaselineStartDate

Baseline Work NA Baseline Work Budgeted Labor Units Calculated NA NA NA BaselineWork

NA

BCWP (EV) NA BCWP BCWP (EV) Calculated Calculated NA NA NA

NA

BCWS (PV) NA BCWS Calculated NA NA NA NA NA

NA

Budget Cost NA Baseline Cost Calculated Cost[Budget] Calculated NA NA BudgetCost

NA

CAM-EAC NA NA NA NA NA NA NA NA

NA

Critical OnCriticalPath Critical Critical Critical Critical_Activity ProjectScheduleTask. CriticalPathIndicator Calculated Critical

OnCriticalPath

Description Name Name Activity Name Description Activity Desc. ProjectScheduleTask.Description Description Description

Name

EAC NA EAC EAC NA NA NA NA

NA

Early Finish EarlyFinishDate Early Finish Early Finish Early Finish Early Finish EarliestScheduledBasePeriod. Finish NA EarlyFinish

EarlyFinishDate

Early Start EarlyStartDate Early Start Early Start Early Start Early Start EarliestScheduledBasePeriod. Start Early Start EarlyStart

EarlyStartDate

ETC NA NA NA NA NA NA NA NA

NA

Excluded NA IsActive NA NA NA NA NA NA

NA

Finish CurrentFinishDate Finish Finish Finish Early Finish CurrentScheduledBasePeriod. Finish Calculated Finish

CurrentFinishDate

Free Float FreeFloatDuration Free Float Free Float Free Float Free Float Free Float Free Float Free Float

FreeFloatDuration

ID ID ID Activity ID ID Activity ID ProjectScheduleTask.Name Activity Name ID

ID

Late Start LateStartDate Late Start Late Start Late Start Late Start Late Start Late Start LateStart

LateStartDate

Late Finish LateFinishDate Late Finish Late Finish Late Finish Late Finish Late Finish Late Finish LateFinish

LateFinishDate

LIKELY NA NA NA NA NA NA NA NA

NA

Longest Path OnDrivingPath Critical Longest Path Critical Critical NA Calculated Longest Path

OnDrivingPath

MOD NA NA NA NA NA NA NA NA

NA

Number of Lags Calculated Calculated Calculated Calculated Calculated ProjectScheduleTaskRelationship. LagTimeMeasure NA Calculated

Calculated

Number of Leads Calculated Calculated Calculated Calculated Calculated Calculated NA Calculated

Calculated

Number of FF Predecessors Calculated Calculated Calculated Calculated Calculated Calculated NA Calculated

Calculated

Number of Predecessors Calculated Calculated Calculated Calculated Calculated Calculated NA Calculated

Calculated

Number of SF Predecessors Calculated Calculated Calculated Calculated Calculated Calculated NA Calculated

Calculated

Number of SS Predecessors Calculated Calculated Calculated Calculated Calculated Calculated NA Calculated

Calculated

Number of Successors Calculated Calculated Calculated Calculated Calculated Calculated NA Calculated

Calculated

Original Duration BaselineDuration (if unavailable, map to CurrentDuration) Duration Original Duration Original Duration Original Duration TotalDurationMeasure Duration

BaselineDuration (if unavailable, map to CurrentDuration)

OTB NA NA NA NA NA NA NA NA

NA

P50 Cost NA NA NA P50 Cost NA NA NA NA

NA

P50 Finish NA NA NA P50 Finish NA NA NA NA

NA

P50 Start NA NA NA P50 Start NA NA NA NA

NA

P80 Cost NA NA NA P80 Cost NA NA NA NA

NA

P80 Finish NA NA NA P80 Finish NA NA NA NA

NA

P80 Start NA NA NA

NA

Percent Complete CalculatedPercentComplete % Complete Calculated Percent Complete Calculated ProjectScheduleTask. CalculatedCompletionPercent NA PercentComplate

CalculatedPercentComplete

Physical % Complete PhysicalPercentComplete NA

PhysicalPercentComplete

PLAN_ACC NA NA NA NA NA NA NA NA

NA

Primary Constraint TaskConstraints. ConstraintTypeID Constraint Type Primary Constraint Primary Constraint Calculated Primary Constraint Calculated PrimaryConstraint

TaskConstraints.ConstraintTypeID

Primary Constraint Date TaskConstraints. ConstraintDate Constraint Date Primary Constraint Date Primary Constraint Date Calculated Primary Constraint Date Calculated PrimaryConstraintDate

TaskConstraints.ConstraintDate

Project Finish ProjectScheduleData. CurrentFinishDate Finish Date Finish Data Date Scheduled Finish NA NA ProjectEnd

ProjectScheduleData.CurrentFinishDate

Project Start ProjectScheduleData. CurrentStartDate Start Date Start Start Project Start NA NA ProjectStart

ProjectScheduleData.CurrentStartDate

Project Time Now ProjectScheduleData .StatusDate Status Date Data Date Finish Time Now NA NA EffectiveProgressDate

ProjectScheduleData.StatusDate

Remaining Cost NA Remaining Cost Calculated Cost[Remaining] ETC NA Calculated Remaining Cost

NA

Remaining Duration RemainingDuration Remaining Duration Remaining Duration Remaining Duration Computed Remaining Dur. ProjectScheduleTask. RemainingDurationMeasure Remaining Duration Analyzed Remaining Duration

RemainingDuration

REPLAN NA NA NA NA NA NA NA NA

NA

Risk Input - Duration Description NA NA NA Calculated NA NA NA NA

NA

Risk Input - Duration LowerPcent NA NA NA Calculated NA NA NA NA

NA

Risk Input - Duration Max NA NA NA Risk Input - Duration Maximum NA NA NA NA

NA

Risk Input - Duration Mean NA NA NA Risk Input - Duration Mean NA NA NA NA

NA

Risk Input - Duration Min NA NA NA Risk Input - Duration Minimum NA NA NA NA

NA

Risk Input - Duration MostLikely NA NA NA Risk Input - Duration MostLikely NA NA NA NA

NA

Risk Input - Duration MostlikelyPcent NA NA NA Calculated NA NA NA NA

NA

Risk Input - Duration Notes NA NA NA Risk Input - Duration Notes NA NA NA NA

NA

Risk Input - Duration Risk Distribution NA NA NA Calculated NA NA NA NA

NA

Risk Input - Duration RiskFunction NA NA NA Calculated NA NA NA NA

NA

Risk Input - Duration RiskId NA NA NA Calculated NA NA NA NA

NA

Risk Input - Duration RiskOn NA NA NA Calculated NA NA NA NA

NA

Risk Input - Duration Shape NA NA NA Calculated NA NA NA NA

NA

Risk Input - Duration StdDeviation NA NA NA Calculated NA NA NA NA

NA

Risk Input - Duration UpperPcent NA NA NA Calculated NA NA NA NA

NA

Risk Input - Probabilistic Description NA NA NA Calculated NA NA NA NA

NA

Risk Input - Probabilistic Notes NA NA NA Calculated NA NA NA NA

NA

Risk Input - Probabilistic RiskFunction NA NA NA Calculated NA NA NA NA

NA

Risk Input - Probabilistic RiskId NA NA NA Calculated NA NA NA NA

NA

Risk Input - Probabilistic RiskOn NA NA NA Calculated NA NA NA NA

NA

Risk Input - Probabilistic Links Description NA NA NA Calculated NA NA NA NA

NA

Risk Input - Probabilistic Links Notes NA NA NA Risk Input - Probabilistic Links Notes NA NA NA NA

NA

Risk Input - Probabilistic Links RiskFunction NA NA NA Calculated NA NA NA NA

NA

Risk Input - Probabilistic Links RiskId NA NA NA Calculated NA NA NA NA

NA

Risk Input - Probabilistic Links RiskOn NA NA NA Calculated NA NA NA NA

NA

Risk Input - Task Existence Description NA NA NA Calculated NA NA NA NA

NA

Risk Input - Task Existence Notes NA NA NA Risk Input - Task Existence Notes NA NA NA NA

NA

Risk Input - Task Existence RiskFunction NA NA NA Risk Input - Task Existence Function NA NA NA NA

NA

Risk Input - Task Existence RiskId NA NA NA Calculated NA NA NA NA

NA

Risk Input - Task Existence RiskOn NA NA NA Calculated NA NA NA NA

NA

Risk Input - Task Existence Probability NA NA NA Risk Input - Task Existence NA NA NA NA

NA

Risk Output - CostSensitivity NA NA NA Risk Output - CostSensitivity NA NA NA NA

NA

Risk Output - CostStdDeviation NA NA NA Risk Output - CostStdDeviation NA NA NA NA

NA

Risk Output - CriticalityIndex NA NA NA Risk Output - CriticalityIndex NA NA NA NA

NA

Risk Output - DurationCruciality NA NA NA Risk Output - Duration Cruciality NA NA NA NA

NA

Risk Output - DurationStdDeviation NA NA NA Risk Output - DurationStdDeviation NA NA NA NA

NA

Risk Output - DurationSensitivity NA NA NA Risk Output - DurationSensitivity NA NA NA NA

NA

Risk Output - MeanCost NA NA NA Risk Output - MeanCost NA NA NA NA

NA

Risk Output - MeanDuration NA NA NA Risk Output - MeanDuration NA NA NA NA

NA

Risk Output - MeanFinish NA NA NA Risk Output - MeanFinish NA NA NA NA

NA

Risk Output - MeanStart NA NA NA Risk Output - MeanStart NA NA NA NA

NA

Risk Output - PercentageTaskExisted NA NA NA Risk Output - % Iterations Existed NA NA NA NA

NA

Risk Output - ScheduleSensitivityIndex NA NA NA Risk Output - ScheduleSensitivityIndex NA NA NA NA

NA

Schedule OBS

(Anything mapped to this field is not read in from the schedule)

OBSElementID NA NA NA NA NA NA NA

OBSElementID

Schedule WBS

(Anything mapped to this field is not read in from the schedule)

WBSElementID NA NA NA NA NA NA NA

WBSElementID

Secondary Constraint TaskConstraints. ConstraintTypeID NA Secondary Constraint NA Calculated Secondary Constraint Calculated SecondaryConstraint

TaskConstraints.ConstraintTypeID

Secondary Constraint Date TaskConstraints. ConstraintDate NA Secondary Constraint Date NA Calculated Secondary Constraint Date Calculated SecondaryConstraintDate

TaskConstraints.ConstraintDate

Start CurrentStartDate Start Start Start Early Start CurrentScheduledBasePeriod. Start Calculated Start

CurrentStartDate

Task Planning Level ID

Task Planning Level ID

NA

NA

NA

NA

NA

NA

NA

Task Planning Level ID

Task Subtype ID

Task Subtype ID

NA

NA

NA

NA

NA

NA

NA

Task Subtype ID

Total Cost NA Cost Calculated Cost[Total] Calculated NA NA TotalCost

NA

Total Float TotalFloatDuration Total Slack Total Float TotalFinshFloat Total Float ProjectScheduleTask. TotalFloatDurationMeasure Total Float Total Float

TotalFloatDuration

WBS Code WBSElementID Outline Number WBS Work Breakdown Structure NA NA NA WbsCode

WBSElementID

WBS Name NA (unless IPMDAR Cost is loaded) Outline Number WBS Name Work Breakdown Structure NA NA NA WbsName

NA (unless IPMDAR Cost is loaded)

WORST NA NA NA NA NA NA NA NA