Display a Second Bar on the Gantt Chart

Display a second (bottom) bar on the Gantt chart. This enables the Bottom Bar options on the SmartGantt Configuration dialog box.

To display a bottom activity bar on the Gantt chart, complete the following steps:

  1. Select the S1 // Projects tab.
  2. In the Activities group, click the SmartGantt drop-down arrow.
  3. Click the Bottom Bar command. The bottom bar command is highlighted and the bottom bar for each activity displays in the Gantt chart.