Change Time Now and Update Progress
Change time now for a project and update progress.
To change Time Now and update progress, complete the following steps:
- Select the S1 // Projects tab.
- Select a project in the Activities view.
- In the Details pane, on the Status tab, click the ellipses in the Time Now field.
- On the Change Time Now and Update Progress dialog box, click the Time Now field drop-down arrow to select a different Time Now setting.
- In the Activity Progress group, select whether you want to automatically progress work as planned or reschedule uncompleted work to start after Time Now.
- Click OK.