Activity View on the S1 // Projects Tab

The Activity view is the standard view after importing a project. This view displays all activities, along with each activity attribute including start/finish dates, remaining duration, calendar, and activity status.

External Activities

If you have imported external activities from Microsoft Project, they display in gray. If you select one, you can see the predecessor/successor information on the Activity Relationships tab.

Calibrating Activities

You can calibrate each activity using the duration calibration slider which allows you to calibrate the activity duration and immediately view the impact on the rest of the schedule .

Creating Activity Filters

You can create filters for the Activities View and SmartGantt using metrics or during forensic analysis.

Filtering the Activity Grid Data

The Activity grid includes a filter row just below the column header row (Salmon-colored row). You can enter text in this row for any column to filter the grid data. As you enter filter text, a filter box displays below the Activity grid. This box includes the column header and the filter entry on the left, and edit and delete icons on the right.

Filter Box

  • Click the down-arrow on the filter to select alternate filter options.
  • Click Filter Delete Icon to delete the filter.
  • Click Filter Editor Icon to edit the filter using expressions and a picklist.

This Activity grid filter is available on both the S1 // Projects and S3 // Risk tab.