Use the Risk Sensitivity Report

This report evaluates the relationship between durations and/or costs by creating a scatter chart showing their interaction.

The X-axis and Y-axis must be defined in order to use the Risk Sensitivity report.

To run the Risk Sensitivity report, complete the following steps:

  1. Select the S3 // Risk tab.
  2. In the Views menu, click Right Panel > Risk Sensitivity.
  3. On the Risk Sensitivity configuration screen, select activities and values for each activity to view their relationship.
  4. Click Analyze to create the Risk Sensitivity report.