Create a risk-adjusted schedule based on risk outputs.
To create a risk-adjusted schedule based on risk outputs, complete the following steps:
-
Select the S3 // Risk tab.
-
With the project selected in the Projects pane, in the Analysis menu, click
Build Scenario.
-
Select
Scenario Based on Risk Outputs, then edit the
P Schedule value if needed.
-
In the Analysis menu, click
Run Risk Analysis.