Create a risk-adjusted schedule based on risk inputs.
To create a risk-adjusted schedule based on risk inputs, complete the following steps:
-
Select the S3 // Risk tab.
-
With the project selected in the Projects pane, in the Analysis menu, click
Build Scenario.
-
Select
Scenario Based on Risk Inputs, then select either
PERT or
Distribution Median.
-
In the Analysis menu, click
Run Risk Analysis.