Create a Risk-Adjusted Schedule Based on Risk Inputs

Create a risk-adjusted schedule based on risk inputs.

To create a risk-adjusted schedule based on risk inputs, complete the following steps:

  1. Select the S3 // Risk tab.
  2. With the project selected in the Projects pane, in the Analysis menu, click Build Scenario.
  3. Select Scenario Based on Risk Inputs, then select either PERT or Distribution Median.
  4. In the Analysis menu, click Run Risk Analysis.