Reports
Use the screens under Reports to generate the Earned Value, Estimate to Complete, Labor Estimate to Complete, Project Budget Detail, and Project Budget Summary reports.
Related Topics:
Use this screen to print the earned value report for each project node or for a total project. Total budget, ITD budget, ITD actuals, % complete, schedule variances, backlog, and earned value are printed.
Print Estimate to Complete Report
Use this screen to print project budgets that include your selection of a percent complete figure.
Print Labor Estimate to Complete Report
Use this screen to print project budgets that include your selection of a percent complete figure.
Print Project Budget Detail Report
Use this screen to print Labor, unit, and ODC budget information.
Print Project Budget Summary Report
Use this screen to print total amounts for the selected project budget. Print baseline, workplan, and actual costs side by side.