Costpoint Help

Project Cost Detail Subtask

Use this non-editable subtask to view cost detail for a given row. It displays the same information as the main screen but provides a row for each cost element.

This subtask displays information updated by the Compute Estimate to Complete screen.

Contents

Field Description
Proj This field displays the project ID from the main screen.
Proj Name This field displays the project description.
Owning Organization This field displays the owning organization from the main screen.
Owning Organization Name This field displays the owning organization description.
Proj Manager This field displays the name of the project manager from the main screen.

Date Updated

Use this group box to assess the age of the data in the inquiry.

Field Description
Incurred The date on which the Update Incurred Cost for ETC process was last executed is displayed.
Previous Estimate The date on which the Compute Estimate to Complete process was last executed is displayed.
Fiscal Year This field displays the fiscal year for which information was updated.
Period This field displays the period for which information was updated.
Subpd This field displays the subperiod for which information was updated.
Rate Type The rate type, actual or target, that was used on the Update Incurred Cost for ETC process is displayed.
Contract Value This field displays the contract value from the Manage Modifications screen.

Proj Cost Detail

Information is provided for each direct cost account and each burden pool, along with a fee line. This information is categorized under the following headings: Description, Total Costs Incurred, Estimate To Complete, LREAC, Base Budget, Variance, Percent Complete, Commitments, Percent Complete With Commitments.

Field Description
Description This non-editable field displays the account or pool description.
Total Costs Incurred This field displays the total cost-incurred amount for the selected project.
Estimate-To-Complete This field displays the total estimate-to-complete amount for the selected project.
LREAC This field displays the total LREAC amount for the selected project.
Base Budget This field displays the base budget amount for the selected project. This amount is the total budget for this project/account/org on the Manage Project Total Budget screen.
Variance This field displays the variance amount, which is calculated by subtracting the LREAC from the Base Budget for the selected project.
Percent Complete This field displays the percentage of the project which has been completed.
Commitments This field displays the commitment amount for the project. The commitment amount is the total of outstanding purchase orders.
Percent Complete With Commitments This field displays the total percent complete, including commitments.