Use this screen to Update the Project Status of the project ID selected in the Navigation, and all lowest level project IDs under the selected ID. You must update the project status of the project ID for each period of the project's period-of-performance from the start date up to, and including, the last closed period on a cum basis.
You can select a project number, then select fiscal year from the FY-Period drop-down list. A table displays below with period end date, % completed, and approval status (y/n). You can update the % Completed after clicking Edit next to the appropriate period end date.
EV Status
Update the Task Status