This topic describes the cost information that displays in the detail tables of the Project Cost screen for the Cost report type.
This table displays summary cost information by element (for example, labor, materials, subcontractor, and so forth) for level-down projects.
Column Headings |
Description |
Project |
This column displays the Proj ID numbers that you are allowed to see based on the your security org ID. |
Project Title |
This column displays the project title. |
Manager |
The name displayed in this column derives from the Project Manager field in the Contract Master. |
Start |
This column displays the project start date. |
End |
This column displays the project end date. |
Funding |
This column displays the funding amount. |
Remaining |
This column displays the amount remaining. |
ITD Var |
This column displays cost variance information from the date the project started to the current date. |
Commit |
The numbers in this column reflect unposted labor and the unfulfilled amounts from open purchase orders. |
Month/Year |
This column starts with the most current closed period and then shows the past six periods of data. |
To view Burdened Cost Breakdown Category details, see the following: