BUYER DASHBOARD

Use this screen to view and/or update information regarding purchase orders (PO). The Buyer Dashboard has dashparts that will give buyers a view of POs that require their actions. From the dashboard, buyers can use the hyperlink to access a particular PO/line/delivery schedule line, and take the necessary action. For example, the buyer can accept the quantity and due date changes proposed by the supplier. Buyers can also add notes, via this portal, to communicate with the supplier. In addition, buyers can update PO line information manually or via an action type for certain changes that have been accepted by the supplier. Security validation based on the authorized organization for the logged-in user applies to this screen.

You need to save the default/defined parameters the first time you access the dashboard.

To save the default/defined parameters:

  1. Click Materials » Purchasing » Dashboards/Actions » Buyer Dashboard » Parameters | Reports.

  2. To access the Dashboard Options, click the Parameters from the breadcrumb trail.

  3. Set the dashboard parameter ranges.

  4. Click Save or Save & Continue to save the parameters.

The screen opens to a dashboard with several dashparts that display POs based on the following conditions:

From the dashboard, buyers can use the hyperlink to access a particular PO/line/delivery schedule line, and take the necessary action. For example, the buyer can accept the quantity and due date changes proposed by the supplier.

Buyers can also add notes, via this portal, to communicate with the supplier. In addition, buyers can update PO line information manually or via an action type for certain changes that have been accepted by the supplier.

The information on each dashpart is based on the following conditions:

The Pending Buyer Action (across Purchase Orders and by Purchase Order) dashparts are available only to users who are licensed for Supplier Portal.

Location

Dashparts

Pending Buyer Action (across Purchase Orders)

This dashpart has bars that indicate the number of PO lines/delivery schedule lines exist in states that need buyer action. You can click the bar hyperlink to go to the Manage Buyer Action screen where the corresponding PO/PO lines are loaded.

Past Due Deliveries

This dashpart has bars that indicate the number of days that the supplier is late in fulfilling the PO line order. Click the bar hyperlink to go to the Manage Buyer Actions screen, where the corresponding PO/PO lines are loaded. By default, the ranges for this dashpart have been set to increments of 10 (Ex. 10, 20, and 30, respectively, for ranges 1-3). You can set the ranges by clicking Parameters from the breadcrumb trail (Materials » Purchasing » Dashboards/Actions » Buyer Dashboard » Parameters » Reports) and define up to 10 ranges for this dashpart. Costpoint will only display those that have been defined, and you have an option to hide this dashpart.

≤ 10 Days

This bar indicates the number of PO lines or delivery schedule lines (across multiple POs) that are late by up to 10 days. If this screen is opened by selecting ≤ 10 bar on the dashboard, Costpoint loads all PO lines that match the company and buyer ID with that of the logged-in user that are overdue by 10 days or less, and have an open PO line status.

11–20 Days

This bar indicates the number of PO lines or delivery schedule lines (across multiple POs) that are between 11-20 days late. If this screen is opened by selecting 11–20 bar on the dashboard, Costpoint loads all PO lines that match the company and buyer ID with that of the logged-in user that are overdue by 20 days  or less, and have an open PO line status.

21–30 Days

This bar indicates the number of PO lines or delivery schedule lines (across multiple POs) that are between 21-30 days late. If this screen is opened by selecting > 20 bar on the dashboard, Costpoint loads all PO lines that match the company and buyer ID with that of the logged-in user that are overdue by 30 days  or less, and have an open PO line status.

> 30 Days

This bar indicates the number of PO lines or delivery schedule lines (across multiple POs) that are over 30 days late. If this screen is opened by selecting > 30 bar on the dashboard, Costpoint loads all PO lines that match the company and buyer ID with that of the logged-in user that are overdue by more than 30 days, and have an open PO line status.

Pending Release to Supplier (by Purchase Order)

This dashpart displays a list of POs that have at least one (1) PO line, with or without delivery schedule lines, that has not been released to the supplier. Click the PO hyperlink to go to the Manage Buyer Actions screen, where the corresponding PO/PO lines are loaded for the selected PO. Costpoint loads all PO lines that match the company and buyer ID with that of the logged-in user, PO line/delivery line last action is blank, and PO line status is Open.

Pending Buyer Action (by Purchase Order)

This dashpart displays a list of POs that have at least one (1) PO line or delivery schedule line with pending buyer action. Click the PO hyperlink to go to the Manage Buyer Actions screen, where the corresponding PO/PO lines are loaded for the selected PO. Costpoint loads all PO lines that match the company and buyer ID with that of the logged-in user, PO line/delivery line last action is not blank, and PO line status is Open.

Open Purchase Orders

This dashpart displays a list of POs that have at least one (1) open PO line, regardless of the Last Action value. Click the PO hyperlink to go to the Manage Buyer Actions screen, where the corresponding PO/PO lines are loaded for the selected PO. Costpoint loads all PO lines that match the company and buyer ID with that of the logged-in user, PO line/delivery line last action is not blank, and PO line status is Open.