Use this screen to run a report that displays estimated labor cost for hours charged by Employee to the selected project. The estimated cost is based on hours multiplied by the employees hourly rate and does not take into account Total Time Accounting adjustments.
In the Dates field, click to select the week.
Select this check box to display combined lower level project details in the grid.
Enter the project ID, or click to select it.
After you select the Project ID and set other options, click to populate the Names table.
Click Accounts link to display lower level details.
The table below describes the columns that display for the Names and Account table.
Column Headings |
Description |
Project |
This column displays the project number. |
Name |
This column displays the employee name |
Acct |
This column displays the labor account number. |
Category |
This column displays the labor category. |
Status |
This column displays the status. |
Total Hours |
This column displays the total hours. |